Required reporting, permits, sampling complete |
B: 165. Environmental Compliance |
|
04/30/2020 |
04/30/2020 |
Effective implementation management and timely contract administration |
C: 119. Administrative activities for Chief Joseph Hatchery Maintenance and Operations |
|
04/30/2020 |
04/30/2020 |
Implement short and long term maintenance program for Chief Joe Hatchery facilities and equipment |
D: 61. Implement Maintenance Program for Chief Joseph Hatchery Program |
|
04/30/2020 |
04/30/2020 |
Broodstock collection and transportation to Chief Joe Hatchery |
E: 66. Prepare/Implement BY19 Broodstock Collection of spring & summer/fall Chinook for Chief Joe Hatchery |
|
10/31/2019 |
09/30/2019 |
Fish health sampling, monitoring and maintenance of health issues |
F: 60. Maintain Fish Health |
|
04/30/2020 |
04/30/2020 |
Hold, sort, spawn, incubate, and pond actions for BY19 Spring Chinook |
G: 176. BY19 Holding/sorting/spawning/incubate/pond Spring Chinook |
|
04/30/2020 |
02/27/2020 |
Hold, sort, spawn, and incubation actions for BY19 summer/fall Chinook |
H: 176. BY19 Holding/sorting/spawning/incubation summer/fall Chinook |
|
04/30/2020 |
03/31/2020 |
Rearing actions for BY19 summer/fall Chinook |
I: 176. BY19 Rearing of summer/fall Chinook |
|
04/30/2020 |
04/30/2020 |
BY18 rearing/acclimation/release of sub-yearling Chinook |
J: 176. BY18 Rearing/acclimation/release of sub-yearling summer/fall Chinook |
|
09/30/2019 |
|
Tag approximately 1,000,000 BY18 yearling summer/fall Chinook at CJH (May 1, 2019 - September 30, 2019) |
L: 158. Apply CWT to BY18 yearling summer/fall Chinook Production at CJH |
|
10/07/2019 |
10/04/2019 |
Tag approximately 400,000 BY18 yearling spring Chinook at CJH (May 1, 2019 - September 30, 2019) |
M: 158. Apply CWT to BY18 yearling spring Chinook production at CJH |
|
09/30/2019 |
06/01/2019 |
Tag approximately 500,000 BY19 hatchery origin sub-yearling summer/fall Chinook at CJH |
N: 158. Apply CWT to BY19 sub-yearling summer/fall Chinook production at CJH |
|
04/30/2020 |
04/30/2020 |
BY18 summer/fall Chinook transfer, rearing, acclimation and release |
O: 176. BY18 Rearing/acclimation/release of yearling summer/fall Chinook |
|
04/30/2020 |
04/16/2020 |
BY18 yearling summer/fall Chinook rearing and release at CJH |
P: 176. BY18 Rearing/release of yearling summer/fall Chinook production at CJH |
|
04/30/2020 |
04/16/2020 |
BY18 Met Comp spring Chinook transfer, rearing, acclimation and release |
Q: 176. BY18 Rearing/acclimation/release of MetComp spring Chinook |
|
04/30/2020 |
04/17/2020 |
Transfer, incubation, rearing actions for BY19 MetComp spring Chinook |
R: 176. BY19 Transfer/incubation/rearing of MetComp spring Chinook |
|
04/30/2020 |
04/30/2020 |
BY18 yearling spring Chinook rearing/release at CJH |
S: 176. BY18 Rearing/release of spring Chinook production at CJH |
|
04/30/2020 |
04/16/2020 |
Apply PIT tags to Summer Chinook production |
T: 158. Apply PIT Tags to Summer Chinook production groups |
|
04/30/2020 |
10/11/2019 |
Apply PIT Tags to Spring Chinook production |
U: 158. Apply PIT Tags to Spring Chinook production groups |
|
10/31/2019 |
10/11/2019 |
Monthly hatchery reports completed. |
V: 141. Other Reports for BPA |
|
04/15/2020 |
04/15/2020 |
Produce an Annual Operation Plan |
W: 174. Produce an Annual Operation Plan |
|
05/31/2019 |
05/01/2019 |